Ethiopia Needs 80 Billion Birr to Complete Africa’s Biggest Dam, GERD

Ethiopia Seeks 80 Billion Birr to Finalize Africa’s Largest Hydroelectric Dam, GERD

According to Grand Ethiopian Renaissance Dam Project Coordination Office, 80 billion birr is required to finalize the remaining construction of the Grand Ethiopian Renaissance Dam (GERD), the largest hydroelectric dam in Africa.

The GERD, whose foundation stone was laid 14 years ago, was initially estimated to cost 80 billion birr.

According to the GERD Project Coordination Office, the construction has reached 97.6% completion, with only a few finishing works remaining.

The Ethiopian public has voluntarily contributed over 20 billion birr toward the construction of the dam thus far. This year, the plan is to raise an additional 1.6 billion birr.

As part of the fundraising efforts, a program involving banks, insurance companies, and credit and savings institutions was held last Friday. Although the event aimed to collect 110 million birr, only 25.9 million birr was raised at that time.

Currently, the GERD is generating 1200 megawatts of electricity using two turbines. Upon completion, the dam’s electricity generation capacity is expected to reach 5,150 megawatts, a significant boost to Ethiopia’s energy sector.

In terms of water storage, the dam presently holds 42 billion cubic meters of water, a figure projected to increase to 74 billion cubic meters when construction is complete.

Since the inception of the project, more than 180 billion birr has been spent on the GERD. To complete the remaining construction, an additional 80 billion birr, equivalent to approximately $635 million, is required. The dam is expected to be fully completed next year.

The GERD is equipped with seven generating units, solidifying its status as Africa’s largest dam in terms of power generation.

However, its construction has been a source of contention among Nile basin countries. Egypt and Sudan have opposed the project since its announcement, citing concerns over water resources.

Despite 13 years of tripartite negotiations, no resolution has been reached. Egypt has blamed Ethiopia for the failure of the talks, alleging inflexibility, while Ethiopia maintains that the negotiations faltered due to Egypt’s insistence on upholding colonial-era agreements that disproportionately favor its interests.

Egypt has once again raised concerns about the GERD at the United Nations Security Council, objecting to Ethiopia’s continued filling of the dam for the fifth consecutive year.

In a formal complaint, Egypt expressed its opposition to Ethiopia’s unilateral actions, arguing that the filling of the GERD violates the 2015 Declaration of Principles signed by Ethiopia, Egypt, and Sudan.

According to the letter sent by Egypt’s Ministry of Foreign Affairs in last Semptember, the fifth filling of the dam disregards the interests of downstream nations, particularly Egypt and Sudan, and poses a threat to regional security.

Ethiopia has officially responded to Egypt’s recent accusations at the United Nations Security Council (UNSC) regarding the Grand Ethiopian Renaissance Dam (GERD).

This development follows Ethiopia’s completion of the fifth filling of the dam’s reservoir and the initiation of additional turbines for power generation.

Ethiopia officially responded to Egypt’s claims in a letter addressed to the then-President of the Security Council, Slovenia on September 6, 2024.

The letter was signed by Ethiopia’s Minister of Foreign Affairs, Taye Atske Selassie.

In the letter, Ethiopia reiterated that the dam’s filling process strictly follows the guidelines established by the tripartite group of experts from Ethiopia, Egypt, and Sudan.

Ethiopia warned Egypt against building projects that could potentially harm other countries, stressing the importance of cooperative and informed decision-making.

The letter also pointed out that Egypt has taken Ethiopia to the UNSC nine times since 2020 over the GERD issue, yet Ethiopia remains committed to resolving the disputes through peaceful dialogue.

By ethionegari@gmail.com

Leave a Reply

Your email address will not be published. Required fields are marked *