Ethiopia started selling electricity to Kenya.
According to the Ethiopian Electricity Authority, electricity sales have officially started today in the Ethiopia-Kenya power transmission line.
The Ethio-Kenya 500 KV power transmission line and converter distribution station, which has been in trial service since October 29, 2022, has been officially put on sale.
This power transmission line is have the capacity to bring in up to 100 million US dollars in annual income, and it has the capacity to transmit up to two thousand megawatts of electricity to countries from Kenya to Tanzania to South Africa, the authority announced.
The Ethio-Kenya power transmission line and converter station project consulting firm, including the cost of compensation and the cost of replacing stolen infrastructure, have cost 500 million US dollars.
Of this, 214.5 million dollars were spent on the construction of the converter station and the ground electrode line, and 120 million dollars were spent on the transmission line.
The construction work of the Ethio-Kenya 500 kV transmission line was done by a Chinese company called “CET”, and the converter distribution station and the ground electrode line were done by a company called Siemens.
The transmission line and protection and data communication line (optical ground fiber) extended through Ethiopia is 440 kilometers long and has 994 high power bearing steel towers.
Ethiopia is already conducting power sales with Sudan and Djibouti, and it will be remembered that it signed a memorandum of understanding with Somaliland, Tanzania, South Sudan and other African countries to sell electricity.
The institution has previously announced that 95.4 million dollars of electricity was exported from Sudan and Djibouti last year.